Levee & Larch · Field
Daily log feed
Crews on site
84
6 jobs · 11 subs
Man-hours logged
612
so far today
Deliveries received
9
3 pending signature
Safety incidents
1
near-miss · reported
  • Field log·6:38a·JOB-2212
    JOB-2212

    Morning huddle · 12-crew concrete pour

    Crew of 12 on site. Slab pour grid B/3–B/8 kicked off 6:30a. Pump truck on time. Two flaggers staged at north gate for concrete trucks.

    RM
    Ray Malveaux · Superintendent
  • Weather·7:12a·Advisory

    Rain advisory issued for Orleans Parish

    60% chance of rain 2p–5p. Wind SW 12 mph. Temp 78° rising to 86°. Exterior pours and roofing work at risk on JOB-2212 and JOB-2214.

    N+
    NWS + on-site sensor · Weather feed
  • Crew·7:45a
    JOB-2212

    Clock-in complete · 84 workers across 6 jobs

    JOB-2212: 34 workers (Delta Concrete 12, Ironworks 6, LL crew 8, Electric 5, Mech 3). Two no-shows from Ironworks — foreman notified.

    T(
    Timekeeper (auto) · Kiosk / geofence
  • Delivery·8:20a·PO-4471
    JOB-2211

    Delivery received · 42 units Type X drywall

    Staged floor 2, east stair. BOL signed. Damaged corner on 3 sheets — photo attached, credit request opened with supplier.

    Sc
    Site clerk — Tanya P. · Receiving
  • AI copilot·8:55a·AI · recommend
    JOB-2212

    Suggested action · protect pour before weather turns

    Given rain probability >55% at 2p and the pour placed 6:30a, curing surface will be vulnerable. Recommend covering B/3–B/8 by 1:30p. Draft directive prepared for Ray M.

    AF
    AI Field Copilot · Auto-generated
  • RFI / Block·9:20a·RFI-088
    JOB-2212

    Blocked · awaiting RFI-088 (fire alarm layout)

    3rd floor east rough-in complete. West rough-in halted pending fire alarm device layout. RFI-088 aging 6 days with Cypress & Iron Architects.

    AR
    Ana Rivera · Electrical foreman
  • Photos·10:02a
    JOB-2213

    Progress photos · plaster restoration bay 2

    12 photos uploaded from bay 2 & 3. Original medallion cleaned; sample skim coat approved by preservation consultant.

    PR
    Priya Ramesh · Project Manager
  • Safety·10:44a·Near-miss
    JOB-2214

    Near-miss reported · unsecured guardrail, unit 214

    Guardrail on unit 214 balcony found loose during morning walk. No injury. Toolbox talk delivered to framing crew. Corrective action logged.

    MG
    Marcus Green · Safety officer
  • Inspection·11:10a·Passed
    JOB-2211

    Rough plumbing inspection PASSED

    Floors 1 & 2 rough plumbing signed off. Sticker photographed and filed. Cleared for insulation and drywall on Monday.

    Co
    City of New Orleans · Inspector — R. Fontenot
  • AI copilot·12:30p·AI · risk
    JOB-2212

    Risk flag · potential scope creep on CE-14

    Change Event #14 (owner-requested dock leveler upgrade) reviewed against contract allowance. Est. cost $47.2K vs. $29K allowance — variance ~$18.2K. Draft change order prepared for Denise K.

    AF
    AI Field Copilot · Auto-generated